Issue Date 7/2/20137/2/2013
Due Date 7/19/2013
Project Title 1000237669 Central Utilities Plant Control Room Renovation
RFQ Text UC San Diego’s Central Utilities Plant (CUP) is located in Revelle College section of campus.  The plant is a 64,000 OGSF structure that consists of a basement, a main floor and a mezzanine.  It was originally constructed in 1963 and currently supplies chilled water, high temperature water, and electricity to the majority of the 12 million square foot campus. The plant houses two 13.5 MW natural gas turbine generators, one 2.8 MW steam turbine generator and has more than 20,000 tons of chilled water generation capacity, and 320,000 lb/hr of steam boiler capacity.  The electricity, chilled water, and high temperature water are distributed to the campus via an underground tunnel system.  The CUP control room is the hub of monitoring these utilities, both inside the plant and out on the campus and is occupied 24/7 by one plant operator, and periodically by a second operator who is based on the plant floor.

UC San Diego will be selecting an Executive Architect to perform programming, planning, design, cost estimating, bid, and construction phase services for the interior renovation for a major control room renovation to occur in phases, with input and guidance from the plant operating and in-house Facilities Management personnel. Note that internal programming sessions have already taken place and the remaining effort can be highly focused. Some of the main components will include the design of a combination main control room along with a multipurpose/chart room/conference room.  
The objective is to have the work complete and occupied in February, 2014. The estimated construction cost budget for the total project is $800,000.

Please see below to access the following documents:  Request for Qualification package, University Form Attachment A & B, and a sample Standard Form 330 for your use if you choose to submit a proposal. 
 
Proposals are due no later than 4:00 p.m., Friday, July 19, 2013.

Final selection and appointment is contingent upon project approval.

UC San Diego encourages the participation of Small, Disadvantaged, Minority-owned, Women-owned and Service/Disabled Veteran-owned Business Enterprises (S/D/M/W/DVBE’s) and is committed to promote a diverse pool of firms for our building programs.

Every effort will be made to ensure that all persons have equal access to contracts and other business opportunities with the University within the limits imposed by law or University policy.  Each candidate firm may be required to show evidence of its equal employment opportunity policy.

Phase CompleteComplete
Selection Process E/A SelectionE/A Selection
Download CUPRFQ.pdf
  
  
  
  
Architects Mosher Drew4206 W. Point Loma Blvd., Suite 200, San Diego, CA 92110619.223.2400Bill Magnuson
Cyrus Cowasjee Architects, Inc.806 Bluffcrest Lane, Encinitas, CA 92024760.201.6478Cyrus Cowasjee
Richard Yen & Associates3515 Hancock Street, Suite 250, San Diego, CA 92110619.224.3605Richard Yen
  
  
  
  
Richard Yen & Associates3515 Hancock Street, Suite 250, San Diego, CA 92110619.224.3605Richard Yen