Project Title Multiple Buildings Electrical Distribution System Upgrade
RFQ Text The University of California, San Diego, will be selecting an Executive Electrical Engineer to perform planning, design, bid, and construction administration phase services for the replacement of an Electrical distribution system.

This project consists of the replacement and upgrade to Electrical Power Distribution Systems but is not limited to: Substations, Normal and Emergency Power Systems, Distribution Network Systems, Generators, ATS’s, Feeder and branch circuiting.
This Electrical Distribution upgrade will include the following Project and Locations:

1. 1000419183 - Muir Biology Electrical Distribution system & network
  a. Construction Cost Budget $1,450,000
2. 1000419185 - MTF Electrical Distribution system & network
  a. Construction Cost Budget $2,200,000
3. 1000419191 - Hubs Hall Electrical Distribution system & network
  a. Construction Cost Budget $2,000,000
Phase CompleteComplete
Selection Process E/E SelectionE/E Selection
Download Multi Electrical - RFQ.pdf
  
  
  
  
Engineering Design Solutions 12396 World Trade Drive, Suite 103, San Diego, CA 92128858.613.0447
The Engineering Partners, Inc.9565 Waples Street, Suite 100, San Diego, CA 92121858.824.1761
Glumac4445 Eastgate Mall, Suite 200, San Diego, CA 92121858.812.5622
Turpin & Rattan Engineering4719 Palm Avenue, La Mesa, CA 91941619.466.6224
  
  
  
  
Engineering Design Solutions 12396 World Trade Drive, Suite 103, San Diego, CA 92128858.613.0447
There are no items to show in this view.